Building Permits in Westminster

Last updated: Verified:

Building Permits in Westminster

Westminster's Building Division operates a paperless permitting process through eTRAKiT for applications, plans, inspections and results.

Current requirements

The City states that permits must comply with the 2026 NEC effective August 1, 2026. Other adopted building-code editions and local amendments should be confirmed on the City's current Code Information resources for the project type.

Review timing

Westminster currently publishes 30 business days for initial commercial building-permit review and 15 business days for subsequent commercial reviews. These figures are not applied to residential or other permit types.

Inspections

Next-business-day inspection requests have a 4 p.m. scheduling deadline. The City expressly notes that inspection windows are not guaranteed.

Fees and professional requirements

Building fees depend on permit type and valuation and are published in City fee schedules. Colorado professional-design requirements vary by scope; no universal seal requirement is stated here.